Construction Update


Main Gym Lobby: 
  • Structural steel erection is com-plete.
  • Metal stud framing is in progress.
  • Roofing installation is scheduled to begin on 11/21.
  • Aluminum curtain wall/window system installation will begin on 12/5.

Humanities Building:
  • Metal stud framing is in progress.
  • Sheet rock installation is in progress on the ground floor.
  • Exterior sheathing is nearly complete.
  • Lathe installation for the exterior stucco system is complete on the west half of the building. Installation on the east end of the building will begin on 11/28.
  • Window installation is complete on the west half of the building and in progress on the east half.
  • Roofing is in progress and should be complete in the next 2 weeks.
  • Mechanical, electrical and plumbing rough in is complete on the ground floor and nearly complete on the 2nd floor.
  • Site concrete work is in progress in various locations around the site.
Theater:
  • Metal stud framing in the basement is in progress.
  • Structural steel erection for the new mezzanine area is complete. Steel erection inside the large theater and above the main stage is in progress.
  • Metal roof installation is complete above the large theater.
  • Roofing above the small theater is ongoing and should be com-pleted by 11/18. 
  • Mechanical, electrical, plumbing and fire sprinkler installation is in progress through out the large and small theater buildings.
Humanities Arts Satellite Building:
  • Metal stud framing is in progress.
  • Roofing is scheduled to begin on 11/21.
  • Mechanical, electrical and plumbing rough in is nearly com-plete at the interior walls.